Unit Prices Used for the Extra Work

Educational overview only. Prudent Guardian (www.inspirecodingedu.com) is not an insurance company, broker, law firm, or registered investment adviser, and does not provide personalized insurance, investment, tax, medical, or legal advice. Verify details with licensed professionals and official issuers.

The backup uses unit prices. The contract has a unit-price list. You cross-reference line items on your recent extra work pay record against both sets of figures to spot mismatches before you submit the draw package. A smudge on the third page of the backup blurs the hourly rate for skilled concrete labor, so you lean in to make out the handwritten notation next to it.

Line Item Alignment for This Extra Work Pay Record

You start by pulling up the digital copy of your signed contract’s unit price schedule to compare against each line listed on the extra work pay record in front of you. Every line item for work performed outside the original scope maps to a corresponding unit type, whether that’s per hour of skilled or unskilled labor, per cubic yard of poured concrete or delivered aggregate, per linear foot of installed piping or exterior siding, or per square foot of finished flooring or laid roofing material. You flag any line that does not have an exact match in the contract schedule to note for further clarification, so you avoid submitting figures that do not align with pre-agreed pricing terms that both parties signed off on before the project broke ground. You can log flagged items directly to your project folder if you use Draw Jacket to centralize all pay-related documentation for the job.

Unit Prices Used for the Extra Work
The folder is shut. The room is ordinary.

Documented Quantity Validation Process

You follow a consistent process to verify all quantities listed on the pay record are accurate and supported by signed field documentation, to eliminate discrepancies that could slow down review times. The steps you use for every extra work pay record are:

  1. Pull all signed daily field tickets corresponding to the date range of the extra work listed on the record, and confirm each ticket has a foreman and client representative signature for the work performed that day, no faded or illegible entries, and clear notes about what work was completed during the shift.
  2. Tally all quantities for each unit type across all signed tickets, making sure to exclude any quantities noted as “testing”, “warranty work”, or “non-billable” in the ticket notes section, as those items are not eligible for extra pay per your contract terms.
  3. Cross your tallied total against the quantity listed on the extra work pay record for each line item, and adjust the record if your tally differs by more than 1% of the listed total, to account for minor rounding differences that are common when tallying across multiple shift tickets.
  4. Attach a scanned copy of each relevant daily ticket to the pay record, and add a short note next to each line item listing the ticket numbers that support the quantity claimed, so reviewers do not have to cross-reference multiple unlabeled documents to confirm your totals.
  5. Note any partial quantities for work that is not yet complete as a separate line item, clearly marked as “partial” in the description, so you do not claim payment for work that is still in progress and not yet signed off on by the client’s on-site team.

Illustrative example: If you tally 42.5 hours of skilled electrical labor across 7 signed field tickets, and the pay record lists 41 hours, you adjust the line item to 42.5 hours and note the ticket numbers that support the updated total next to the line.

Rate Consistency Confirmation Checks

You cross-reference each unit price listed on the pay record against the pre-approved unit price schedule in your signed contract, to make sure you are not listing rates higher or lower than what both parties agreed to before work began. For any line items that do not have a pre-agreed rate in the contract, you confirm that the rate listed on the pay record matches the rate you agreed to verbally or via email with the client’s project manager before the extra work was scheduled to start. You add a link to the relevant email thread or a note about the verbal agreement date and attendees next to any non-contract line items, so anyone reviewing the pay record understands how the rate was set and that it was approved by the appropriate stakeholder. You also check that all labor rates include any required burden costs, such as insurance, payroll taxes, and worker’s compensation contributions, so you do not leave those overhead costs unaccounted for in the line item total.

Supporting Backup Attachment Rules

You gather all relevant supporting documentation to attach to the pay record before you submit it for review, to reduce the chance of requests for additional information that can delay processing. This includes scanned copies of signed field tickets, delivery receipts for any materials purchased specifically for the extra work, photo documentation of the work completed at each stage to prove it was performed to specification, and any written or email correspondence confirming formal approval for the extra work to be performed. You organize all attachments in the exact order they correspond to the line items on the pay record, so reviewers can easily cross-reference each line with its supporting proof without sorting through unrelated files. You label each attachment clearly with the line item number it supports, so no one has to search through dozens of documents to find the proof they need to approve a specific line entry.

Final Quick Review Before You Close This File

You run one last high-level check to make sure you have not missed any critical details on the pay record before you wrap up this session. You confirm all line items have matching verified quantities, consistent pre-approved rates, and attached supporting documents that line up with the line entries. You save a dated copy of the full pay record and all attachments to both your local hard drive and your cloud project folder, so you have redundant backup copies if any version gets lost, corrupted, or accidentally deleted during the review process. You close the file on your screen, and you are done with this review session for now.

Next Time You Open This Extra Work Pay Record

When you pull this file up again, you will first review any feedback sent by the client’s review team regarding your submitted pay record. You will address any questions they have about line item quantities, rate calculations, or supporting documentation, using the backup copies you saved today to provide clear, organized proof for any items they flag for further clarity. You will adjust any line items as needed based on agreed-upon revisions, and resubmit the updated record for further review if required by the client’s internal processing rules. You will also add any new field tickets, delivery receipts, or supporting documents for extra work performed after this submission date to the file, so you can include those new line items in your next pay request for the job. If the record is fully approved when you open it next, you will add the approved total to your project’s overall earned revenue tracking sheet to keep your job cost reports and projected cash flow figures up to date for the rest of the project timeline.

(Word count: 1327)